TITLE 【Syllabus of Latest Opinion】Supreme Court en banc Decision 2014Da235189 Decided October 30, 2018 【Payment of Construction】* First draft [full Text]
Summary
In a long-term continuing contract under Article 21 of the former Act on Contracts to which the State is a Party, the total construction period is extended beyond the initially stated term, whether adjustment of contract amount is recognized on the ground of modification of construction period (negative)
Prev 【Syllabus of Latest Opinion】Supreme Court en banc Decision 2018Do7172 Decided October 30, 2018 【Violation of the National Sports Promotion Act (Opening of a Gambling Place, Etc.); Operation of a Gambling Establishment; Violation of the National Sports Promotion Act (Gambling, Etc.); Regular Gambling; Inciting Violation of the Credit Information Use and Protection Act; False Testimony】
Next 【Syllabus of Latest Opinion】Supreme Court en banc Decision 2014Da61654 Decided October 30, 2018【Damages (Etc.)】* First draft
219 Seocho-ro,Seocho-gu,Seoul 06590,Republic of Korea 02-3480-1100